The green light given by the Environmental Impact Assessment (EIA) Commission to projects upgrading lagoon channels and the cruise ship hub marks a critical juncture for the future of the Venetian ecosystem. Behind the narrative of “sustainability”, in the guise of rerouting traffic away from the San Marco Basin, lies a massive infrastructure operation that risks irreversibly compromising the morphodynamic structure of the entire lagoon basin.

The figures involved in the project outline a profound transformation of the seabed. The operations entail moving a total of 6.8 million cubic meters of sediment. Of this amount, over 1.1 million cubic meters will be removed from the Vittorio Emanuele III Channel alone: a waterway abandoned for navigation some fifty years ago that is now slated not only to be deepened to -8 or -9 meters but effectively doubled from its historic width. This would be accompanied by the widening and major maintenance of the Malamocco-Marghera Channel (the Canale dei Petroli).

Leading hydrodynamic studies on the Lagoon highlight how dredging and widening flow channels accelerate the erosion of salt marshes, the loss of fine sediments, and the progressive transformation of a brackish ecosystem into an arm of the open sea. This process of morphological homogenization is compounded by the lucrative business of sludge management: with the historic Tresse Island containment site now full, a new containment facility (“Tresse 2”) must be built. This fuels the lucrative monopoly over sediment management, which has long been controlled by the Mantovani firm, the very company at the center of the most controversial aspects of the MOSE project and other major infrastructure works that drained the public coffers and devastated the local landscape.

From an economic standpoint, the figures reveal a significant surge driven by the interests of industrial sectors. Excavation costs alone (excluding the construction of the new Maritime Station and the surrounding yards) have reached €357 million, far exceeding the €157 million originally estimated in the Ministry of Economy and Finance (MEF) table attached to the implementing decrees of Law Decree 103/2021. This is a massive amount of public resources, partly drawn from the National Recovery and Resilience Plan (PNRR) funds earmarked for the ecological transition. It will only ultimately enrich the usual network of construction firms and lobby groups, led by Confindustria, all eager to profit at the public’s expense.

Serious concerns have also been raised regarding procedural legitimacy concerning the projects. As detailed in an urgent formal notice sent to the Ministry of Culture’s Directorate-General by Professor Andreina Zitelli on behalf of the environmentalist association AmbienteVenezia (text at the bottom of the page), the favorable outcome of the Environmental Impact Assessment (VIA) was announced in the press before the mandatory consultation with the Ministry of Culture and the opinion of the Superintendency had been finalized. This represents a serious procedural overreach that risks reducing heritage protection bodies to mere rubber stamps and undermines the citizens and associations that submitted formal observations during the authorization process.

This situation calls for thinking that is rooted in the territory’s identity and actual geography. The Lagoon is neither a logistics hub serving the industrial needs of Porto Marghera nor an asset for the exclusive use of the island city. It is an indivisible common good that rightfully belongs to the mainland cities — to Mestre and its communities — just as much as to Venice.

Mestre and the mainland already bear the territorial scars of major twentieth-century interventions, marked by the impact and pollution of the Marghera industrial zone. Viewing the Lagoon as a single entity means acknowledging that protection of the seabed, water quality, and defense against erosion are matters that affect the health, safety, and quality of life of those living in both Mestre and Venice. Treating this body of water as an industrial channel to be reshaped to suit the speculative ambitions of the usual predatory actors means repeating the mistakes of the past, and sacrificing the citizens’ future for the sake of profit for the few.

© Commissario straordinario per le crociere Venezia

To Dr. Fabrizio Magani

Director General

Directorate General for Archaeology, Fine Arts and Landscape (DG-ABAP)

Copy to:

The Minister of Culture

Dr. Alessandro Giuli

(At his office)

The AmbienteVenezia Association for the Protection of the Venice Lagoon and Interior, registered in the Municipality of Venice’s Register of Associations under No. 2501, acting through the undersigned Prof. Andreina Zitelli, consultant on environmental procedures (EIA, SEA, IPPC) and former member of the National EIA/SEA Commission,

ATTACHING HEREWITH

the article published today (September 26, 2026) in Corriere della Sera – Corriere del Veneto.

The article reports that the dredging projects in the Venice Lagoon, submitted by the then-Cruise Commissioner/President of the Port Authority, have been approved, and that: “the (Port) Authority learned of the outcome through a formal request for access to records specifically to expedite the timeline while awaiting the formalization of the decrees from the Ministry of the Environment issued in concert with the Ministry of Culture” (sic!).

WISHES TO POINT OUT

the violation of law, given that news of the favorable opinions was released BEFORE the required consultation with the Minister of Culture;

the serious breach of confidentiality rules;

the violation of the principle of equality among the parties participating in the procedure; specifically, all those who submitted observations regarding the projects.

EXPRESSES CONCERN REGARDING THE MARGINALIZATION OF THE MINISTRY OF CULTURE

In a cultural environment as sensitive as the Venice Lagoon—a UNESCO site—the opinion of the Superintendency and the Ministry of Culture appears to have acquiesced to this latest superfluous violation of the lagoon environment’s integrity, a violation that is, in certain respects, contrary to current regulations.

HIGHLIGHTS A VIOLATION OF LAW

To allow large cruise ships to enter the Lagoon via the Malamocco Inlet, the submitted projects and the Environmental Impact Assessment (EIA) opinions (if positive) circumvent the ban on transit within the Venice Lagoon established by Decree-Law No. 45 (converted into law in 2021) to protect the Lagoon itself.

POINTS OUT THE RISK OF MAJOR ACCIDENTS

We call attention to the insufficient consideration given to the risk of accidents along the Malamocco–Marghera Canal caused by the exposure of the large ships’ hulls to prevailing winds.

In light of the foregoing, the Association

AmbienteVenezia

REQUESTS

that the Directorate General carefully examine the EIA opinions regarding the dredging projects for the Vittorio Emanuele III and Malamocco–Marghera lagoon canals, which are aimed at bringing large cruise ships back into the Venice Lagoon and are subject to the Minister’s concurrence, so as to avoid placing the Minister in a position where they might commit an act that is guaranteed to have a negative impact on the Venice Lagoon, as well as one that is culturally inappropriate.

Respectfully, awaiting a response,

Prof. Andreina Zitelli

Back to Ytali Global

Dredging the Lagoon. Approval is a Farce ultima modifica: 2026-09-30T17:20:25+02:00 da MONICA COIN
Iscriviti alla newsletter di ytali.
Sostienici
DONA IL TUO 5 PER MILLE A YTALI
Aggiungi la tua firma e il codice fiscale 94097630274 nel riquadro SOSTEGNO DEGLI ENTI DEL TERZO SETTORE della tua dichiarazione dei redditi.
Grazie!

VAI AL PROSSIMO ARTICOLO:

POTREBBE INTERESSARTI ANCHE:

Lascia un commento